Prepare for the following nighttime ramp closures:Ĭlosure of the southbound I-5 to SR-126 off-ramp is anticipated on Wednesday, March 22 from 9 p.m. Pile driving adjacent to the I-5 bridge at Rye Canyon Road between The Old Road and Avenue Stanford.Ĭastaic Creek bridge deck work in the center median between SR-126 and Hasley Canyon Road.Įlectrical work at southbound SR-126 and Parker Road on- and off-ramps. Equipment includes a directional drilling machine, usage of trucks, forklifts and concrete mixing support.īutte Canyon bridge concrete form removal in the center median between Pico Canyon Road/Lyons Avenue and McBean Parkway, adjacent to Vista Valencia Golf Course. Outside shoulder slope soil stabilization (soil nail installation) in both directions between Weldon Canyon bridge and Calgrove Boulevard. Activities include excavation, backfill, shoring, form and concrete work between SR-14 and Magic Mountain Parkway. Westbound Calgrove Boulevard: Right on the Old Rd, merge onto San Fernando Road, right on Sepulveda Boulevard, merge onto Roxford Street, enter southbound I-5 at Sepulveda Boulevard/Roxford Street on-ramp.Įastbound Calgrove Boulevard: Enter northbound I-5 Calgrove Boulevard on-ramp, exit northbound Lyons Avenue/Pico Canyon Road off-ramp, right on Lyons Avenue, enter southbound I-5 at Lyons Avenue on-ramp.Ĭenter median retaining wall construction and concrete barrier work.

Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. Signage is posted along the detour routes and at the preceding off-ramp. Prepare for intermittent closures of the southbound Calgrove Boulevard on- and off-ramps from 7 p.m. Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Boulevard. Construction access from The Old Road may be utilized.

Gavin Canyon bridge foundation steel rebar, forming and grading work along the northbound outside shoulder between Weldon Canyon Road and Calgrove Boulevard. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Road/Coltrane Avenue. Weldon Canyon Road bridge removal of concrete form work. to support all the below activities on I-5. Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Road from 8 p.m. Road construction on the Metro North County I-5 Enhancements Project will continue March 20 to March 26.